Tuesday, August 14, 2012

Confirmed Site Start, Electrical Box, Retainer walls

27th July - 2nd Soil and Survey Ordered


 7th August 12 - Establishment Surveying
Managed to have a chat with the bloke doing the survey and mentioned that PD was rushing their company to get it done! - Means site start will be soon!!


Click on the link above to view drawing
PM me if you would like to view more details.

We had to request for a Building Variation to have our taps mounted under our laundry sink as oppose to having it on the wall above the sink. That way we can have the Drier stacked on top of our front loader washing machine, and no pipes will be exposed! WIN!

Also, we managed to get a credit back for our S-flashing pipe on the side of our garage wall as we were able to have it run down the rear of the garage. (S-flashing is usually used when the property is right up against the neighbouring property and in order not to cross the boundary, this method of flashing is used)


14th August 12 - Confirmed Site Start!
23rd August Site Start
10th Sept Concrete Pour



16th August 12 - Port-a-Loo/Rubbish cage Delivered



23rd August 12 - Scraping begins
24th August 12 - More earth works & Stakes put in


28th August 12 - Retainer walls put in 



30th August 12 - Electrical Box put in