Tuesday, September 11, 2012

Finished Boxing

I managed to meet Peter from Final Inspect out on site at about 2pm, and the boxing up is almost complete 70%. 
When we got out there, we were told that they'll probably get to it by the end of the day. 
So we decided to part ways and come back at 5.30pm to check on the work.

When we got there, Peter was able to highlight some areas which needed some repair in the membrane. He also ensured that the steel re-enforcements were laid in the right angle and correctly. Part of the garage has not been chaired as well. He immediately got on the phone with the supervisor in-charge of the slab and told him his concerns. He made sure that the concrete guys will be coming out BEFORE the pour to rectify these issues. 


Rear of the property. (Kitchen area)


A very complicated area of the house. Front porch area.


No chairs on waffles yet

Side of garage to neighbouring boundary

So this was the pipe with the pink ring on the OUTSIDE of the slab,
It is apparently the breather hole for the soaker tub which you can see is in
the slab.

Looks like its an early start for me tomorrow. 7am scheduled concrete pour!
Also, it appears that the tape and seals on some of the piping had been broken into. Hopefully no debris has fallen in. 